Monday, January 19, 2009

The steel stair arrives

Bill Curran dropped off the steel stair a couple of days ago. It took about 4 guys to haul it inside as it weighs around 350 lbs. This is the open-riser stair that runs from the first to the second floor. It looks really great. Bill and his guys did a beautiful job. Everything is very precise and the welds are clean and nicely hidden. He won't be dropping off the railings until later, when all the floors are installed and the walls are painted.















There's Bill, in the bottom left corner, admiring his work.

What you see here is the framework for the stair, without the wood treads attached. You can see the two stringers that run the full length and the open steel "frames" at each step. These frames act as a cradle for the wood tread to rest on. The treads will be attached with screws (from below) and will overhang the frames. You can also see that there are steel plates on either end. This is how the stair will be attached to the top and bottom wood headers. When we go to install the final stair, we'll remove the temporary wood stair and hoist the steel stair into place. I think we are going to use the temporary treads from the old stair on the new one until the final treads are ready to go in.

We could not really afford to get the metal stair and railings "powder coated", so the final finish will involve simply cleaning the raw metal with a degreaser and steel wool then applying a coat of beeswax. Although a powder coated finish is very nice, we actually prefer the more natural look of the wax finish, which allows the character of the material to show through.

I am getting ready to plane down the reclaimed timbers that will eventually become the treads. We have a couple of different choices for the wood. We have Pine, Fir, and Oak beams. The Pine might be too soft but the Fir could work. To be honest, I am not much of an Oak fan, mostly due to the look of the grain, but I planed down a scrap piece of a 2.5"x11" oak beam to 2"x10" (our tread size), and it looks amazing.

What's nice is that it appears most of the 100 yr old beams are quartersawn, opposed to plain (or flat) sawn. Most people are used to seeing plainsawn oak which has a very wide, pronounced grain. To find wood this size that was milled in this manner is a treat. Along with it's beauty, quartersawn wood is much more stable and will take a finish better. I brushed a coat of polyurethane on one side of the planed beam and it turned a gorgeous honey color. I snapped a couple of pictures (below) that show the size and color as well as a close-up of the grain. We will most likely end up using this Oak for the treads, but if not, I am sure we'll find a place for it somewhere else in the house.

Saturday, January 17, 2009

Wrapping up the exterior cladding

We are just about finished with the installation of the fiber-cement panels (from Certainteed) the only thing left to do is caulk the joints. The other remaining tasks for the exterior are installing the sunshades and the continuous metal cap flashing at the parapet. You can see in the rear facade image to the left that we have already installed ledgers and metal straps above the windows which will support the weight of the sunshades.

The black plastic downspout at the right side of the image is a temporary solution that will soon be replaced by a smooth galvanized pipe that will empty into a rain barrel. Also, we are planning to paint the cover for the whole house fan (top right) either the same gray color as the fiber-cement siding or black to match the window frames. The sunshades, made of exterior grade FSC spruce, will be left with a natural wood finish.

In the end, we are very pleased with the way the panels look. There was a slight change in the fastening system relative to what was originally intended. We had planned on using nails to fasten the panels (as per manufacturer) but as our contractor began to install the panels, he realized that he was not getting the attachment strength that we needed. A few times the panels began to pull away from the sheathing. The problem was partly due to slight undulations in the surface of the sheathing and partly due to the large surface area of the panels which are 2' x 8' in size.

The fiber-cement panels are very rigid and offer little room for any flexing. They tend to want to flatten back out if the surface is not perfectly flat, eventually breaking the caulk seal. A couple of panels even ended up breaking at the beginning due to the bending stress in addition to the impact of the hammer. We found that attaching the panels with stainless steel screws (which is also approved by the manufacturer) using a hammer drill gave us a much more secure connection.

Due to budget constraints, we are not using a rain screen system (which would involve furring strips or vertical runners and therefore would eliminate the flex issue) but instead we are simply attaching the panels directly to the sheathing, caulking only the top and side joints, while allowing any moisture to find its way down and vent out the bottom of the panels. We're hoping to explore a true rain screen system in the next project, possibly using Vaproshield (opposed to Tyvek, which we used and is great product but is white in color and not great if at all visible) for the waterproof membrane and a recycled composite (like Trex) for the vertical channels.



The image to the left shows where the east wall at the third floor (the party wall) meets our metal mansard roof at the front.




The exposed fasteners are more pronounced than we originally envisioned (the nails would have been flush with the face of the panels), but we love the look of it. The evenly-spaced screw heads along with the softly textured, concrete-colored FC panels are reminiscent of poured-in-place concrete with snap-ties (similar to the image below). We realize the appearance might not appeal to everyone, but we feel it embodies the modern aesthetic of the 'new addition' portion of the house.

Thursday, January 8, 2009

Inspiration from Re-Nest

Stephanie from Apartment Therapy's Re-Nest posted an article today about our project. Check it out here. For anyone who's not familiar with Apartment Therapy, it's a great design resource especially geared towards small spaces. Re-Nest is part of the Apartment Therapy 'family' and focuses on green home design. Since we have a 20-month old son, we also love ohdeedoh for their clever approach to design and children. Be sure to return often as these sites are all updated frequently. Many thanks to our good friend Summer for sending in the suggestion!

The new year is a great time to get inspired and to re-evaluate one of the most important spaces that surrounds us: our home. While trying to take that to heart by undertaking some small projects to update our own house, we've been doing more thinking recently about the types of finishes that we'd like to use in the Montrose House and the overall feel that we'd like the space to reflect. Yes, we are modernists at heart but we also like a house to be warm and livable at the same time. It's a fine line to walk sometimes. More on all this in the upcoming weeks...

Tuesday, January 6, 2009

NBC Channel 10 News segment

Here's a link to the video clip on NBC's site: NBC Philadelphia.com: Greening History. You can also view it right here:



Our 'green renovation' news segment aired bright and early this morning, Wednesday Jan. 07, at 5:45am and 6:45am. It will also air again on Sunday, Jan. 11, at 7:30 am. Thanks to Terry Ruggles of Channel 10 for considering the Montrose House for their segment.

Work on the house slowed considerably over the holiday. Today we're meeting with our contractor at the house to pick up where we left off before the break and determine what outstanding work is left to do on his end. We'll also be heading up to Chinatown to meet with our stair fabricator to iron out some last minute questions on the dimensions and detailing of the steel stair. If all goes well, it should be ready to install by next week! Things are picking back up now and we'll post more updates shortly.

Thursday, December 18, 2008

local news update & next steps

We just received word that the local NBC Channel 10 'Green Rehab' segment should be airing either next Wednesday, December 24th or the following Wednesday, the 31st. We will be posting a copy on the blog, so don't worry if you miss it.

This week we've been continually trying to get PGW to turn on the gas, which has required calling them numerous times. Supposedly the foreman has us on the schedule today (third time this week) to install the meter. Hopefully, today is the day and we'll have some heat!

As soon as all the drywall is mudded and taped and the systems are operational, our contract with Merlin, our GC, will basically end. He'll turn the house over to us to wrap up, as our plan has been to handle purchasing & installing most of the finishes and fixtures ourselves to save money. We will retain Merlin to help us occasionally, as his expertise and advice will be essential in the areas where our experience is lacking. I'll feel much better having him and/or his subs close by when it comes time to install the plumbing fixtures (something we've never done before) and a number of other items. Toilets are one thing you definitely want to get right the first time!

Over the holidays, Merlin's coworker, Nate, will be prepping the drywall openings and pre-cutting most of the trim for the doors and windows. After we get back into town, our first task will be to begin installing the trim around all of the openings. The baseboards won't go in until after the bamboo floors are laid. Our trim detail is going to require quite a bit of work as we are going with what is sometimes called a "museum trim" detail - where the trim board is actually flush with the drywall (opposed to being applied on top of it) and there is a 1/4" reveal where the edge of the trim meets the edge of the drywall. If this sounds confusing, no worries...we will explain this later in more detail.

Bill Curran is now fabricating our steel stair and is set to install before New Year's. This will be quite a milestone and we'll be sure to post before/after and progress photos.

We also have some exciting developments to share related to Southern Liberties branching off into the realm of custom furniture design and fabrication. We'll share more about that in January.

Monday, December 15, 2008

Starting to look like a house...kind of

In case you didn't make it to the Open House, here's shot of what the main living space looks like with most of the drywall up, as of a couple of days ago. You can see the sawhorses and plywood that served as our layout table for the Open House as well as the sections of drywall we left off to show various internal elements of the project. That's Emily casually posing at the bar and providing some scale.












Tomorrow we start on all the prep work for the window and door trim.

Wednesday, December 10, 2008

Thank you...

A big thanks to everyone who braved the cold weather last Saturday to join us at our Open House & Construction Tour. We estimate that at least 60-70 people participated which was an amazing turnout! We've also received emails from quite a few people who weren't able to make it. After the holidays, we'll pick another Saturday afternoon to give anyone else interested in touring the house the opportunity to stop by before we get too much farther along.

Tomorrow morning we're filming a news segment with local NBC news anchor Terry Ruggles about green rehabs in Philadelphia. As soon as we have more information about when the segment will air, we'll post it here!

Next on our plate: ordering the kitchen cabinets, fabricating the custom steel stair, & finalizing the remainder of the plumbing fixtures in the house.

Saturday, December 6, 2008

Open House & Construction Tour today!

Don't forget to stop by this afternoon for our Open House & Construction Tour! We're looking forward to hearing everyone's feedback and suggestions as we enter the next phase of the project and start getting into the installing the final finishes, fixtures, and working out the remaining details.
























While we weren't able to get our furnace hooked up yet, the house will be nice and toasty with a temporary heater in the basement. And Dunkin' Donuts is just a block away if anyone needs to use the facilities.

We're looking forward to being able to work at night and on the weekends, now that we have power. The other night, I saw the house for the first time with lights on through the all windows. I must say...it was pretty impressive. Now that all the masonry openings have been cut along the side and remaining windows are in, the whole building has taken on a much different feel, especially at night. We've made some progress on the water as the meter is installed, but we can't get a temporary sink/toilet hooked up until the sanitary line is completed.

Looking forward to seeing everyone soon!

The sheet rock has been installed

Yesterday the drywall crew arrived bright and early. We were expecting 3-4 workers, but instead a crew of 6 was waiting in front of the house with their tools in hand. We had all the drywall staged in the house the previous day right after it arrived from Green Depot. These guys work amazingly fast. By mid-afternoon, they had finished the 3rd floor, most of the 2nd floor, and were starting on downstairs. Our contractor decided to go with 4'x12' sheets instead of the standard 4'x8' ones. When hanging them horizontally, we ended up with less waste as most walls in the house are not more than 10' or 11' in length.

The bathrooms are wrapped with water-resistant board on both the walls and the ceilings for extra protection (it's not uncommon to find it used only on the walls).

While I knew this stage would be a big milestone in the project, it always surprises me how much drywall can transform a space. No matter how many times I go through this process, it's exciting every time. There's something about being able to 'see' the walls that makes the house seems much more finished than before. We're leaving the drywall as is for now, without taping and mudding the joints as we know that we have just one day before the open house. We also left certain areas open throughout the house, without any drywall, so that people can get a sense of what's underneath and see some of the structure and building systems.

Now for the final clean up....urh,...

Friday, December 5, 2008

Bio-based Insulation in action!

A few days ago, the crew from Northend Barriers arrived with their trendy Bio-Based trailer and generator, ready to knock out our little row house project in just a day.











We were lucky to get them, as Northend is currently booked straight through the spring, installing BioBased on a number of very large jobs. Because our project is several months behind schedule, we were afraid that we might have lost our place on the list. After a few pleading phone calls from us and our contractor, reminding them that we've been in touch periodically with schedule updates, the good guys at Northend finally agreed to fit us in between two of their larger jobs. Two men dressed from head to toe in white jumpsuits arrived mid-morning and stayed on until nearly 9pm to finish the job. The suits are primarily projection to keep the guys clean and adhesive-free. The foam itself is not hazardous to the touch but is very sticky.

Check out this stuff out in action!



After learning more about the cost difference between closed cell and open cell spray foam, we specified a combination of the two for the project, depending on the thickness of the wall, its location, and the desired R-value. By making these changes, we were able to reduce the overall quote by about 40%. The closed cell foam is roughly twice as much money as the open cell, and we had originally planned to use closed cell throughout. Finally, something has turned out to be LESS expensive than we had anticipated. It's a good thing.















































After installation, the foam is shaved off so that it's level with the studs, and fills the void between the studs. In reality, the stuff is rarely perfect as there is some variation in depth and consistency (at least in our case). We had the crew save the scraps, which can be used to fill up any major gaps- such as behind pipes or other hard to reach areas- or thrown into a typical unconditioned attic space to beef up the existing insulation. We have a few quirky spaces where new and old construction meet and were able to fill in a few holes by using the leftovers, and a few cans of that off-the-shelf expandable foam. We still have about 8 bags left in the back yard and will probably offer it up on Craigslist or Freecycle soon.



















By the end of the day, the only casualty was our truck, which had been parked out front for a few hours. Turns out there was a small gap between the brick facade and the cornice. The foam made its way through the crack, through the air outside, and down onto the side of our truck. The foam part came off easily, but the adhesive part was the problem. It looks like it will scrape off of the glass fairly easily with a razor blade, but we're still waiting to hear back from our contact at Northend Barrier (Tom Purcell) to find out how (and if) this stuff can be removed from the truck body without damaging the paint job.

The lessons learned on this job (other than keeping the truck far, far away) are that next time we would strongly consider waiting until the heat is turned on to spray the foam. The next day, we noticed several places where the foam pulled away from the studs about 1/4" due to the temperature differential. The foam is heated and pressurized in canisters before being sprayed into the wall cavities. The house itself was definitely cold, especially so after sundown, when the work continued late into the night. Because of the scheduling difficulties, we were hesitant to wait any longer and it was unclear when the next opportunity would be to get a crew. We filled some of the gaps ourselves the next day but Northend has agreed to come back and hit the larger areas. We decided to hold off on "taping and mudding" the drywall for a few days so we could simply remove the drywall screws and pop the boards off in the areas that need more insulation.

The other downfall to the spray foam is that it could make rewiring extremely difficult (especially the #1701, the closed cell). Also, for architects that are used to working with precise, exact materials, this stuff is not going to be in your comfort zone. The stuff is messy and blobby and the control is modest at best. The overspray can't help but get in places it shouldn't, like J-boxes and around pipes. It has a life of its own. I admit, it does take some getting used to. The performance is where the spray foam excels- we've been able to achieve R-20 in just a 2x4 stud wall. And in a renovation project, we feel comfortable knowing that the foam is going to keep the old envelope (and the new) super tight and efficient.

Monday, December 1, 2008

Drywall...with a conscience

A colleague of mine at Philadelphia University recently told me about a new drywall plant in PA that is actually built right next to a coal-fired power plant in order to readily capture the synthetic gypsum byproduct for use in their drywall. I am looking into sourcing all our drywall from this plant.

United States Gypsum Corporation
Lycoming Mall Dr
Washingtonville, PA 17754
(About 2.5 hours from Philadelphia)

The facility produces wallboard using recaptured gypsum, uses 100 percent recycled paper for the surfaces of the finished wallboard products, recycles 100 percent of its production waste and feature a closed-loop liquid effluent system, which translates to zero discharge into nearby waterways. It was purposefully located right across the road form the Montour (coal-fired) Power Plant. At the power plant, scrubbers (the environmental controls that remove the sulfur dioxide from the emissions of coal-fired power plants) work by spraying a mixture of crushed limestone and water onto the exhaust gas before it goes out the plant’s chimney. The limestone and water react with the sulfur in the plant’s exhaust to form synthetic gypsum, which is collected and shipped to the USG facility that is across the road from the power plant.

OR...if that doesn't pan out

Green Depot actually stocks drywall that contains 95% recycled coal ash that they get from another Pennsylvania drywall plant (also USG, I believe) that employs the same process as the Washingtonville plant, it's just not right across the street from the power plant.

The price per sheet is virtually the same as any other drywall. We are going to look into both options but seeing that we need have drywall on site in two days...it looks like we might be giving Green Depot a call. It's nice to know they're close by.




Sunday, November 30, 2008

Fiber-cement panel mock up

Our sub-contractor (Danny from Longboard Contracting) will begin installing the fiber-cement panels on Monday. I don't know if I mentioned this in an earlier post, but we decided to go with panels by Certainteed. Most fiber-cement products on the market are by James Hardie (as in "Hardiplank") which is a great product. Both Hardi and Certainteed products contain recycled content, are manufactured locally, and are extremely durable. The main reason we decided to go with Certainteed was the fact that, in addition to the recycled content, they guarantee a minimum of 30% recycled fly ash in their mix. Another reason was the better color selection as well as their finish. All pre-finished Hardipanels have a slight sheen that we weren't crazy about.

The irony, of course, is that we eventually chose the unfinished (just primed) panel from Certainteed because the primed finish closely resembled a concrete color had a great subtle texture to it. The image to the left shows the mock-up of the F-C panels and the window trim detail on the rear facade of the house.

Now you do have to eventually finish the panel (either paint or seal) in order to retain the 50 year warranty, but Certainteed gives you a two year window to do this before they'll void their warranty. Hardipanel is also available in a primed finish, but they only give you a 3 month window before you have to finish it. To me, this says something about the manufacturer's confidence in the durability of the raw material, although I am sure that Hardi's product would hold up just fine. Eventually the owner of the house will have to make a decision on whether to paint the panels or simply seal them, if they want to keep the warranty. The beauty of the primed panels is that they could also be painted subtly different colors to form kind of a patchwork pattern, if desired.

Either way, we are excited to see the panels go up as this is the final stage of the exterior cladding. Danny has been great to work with so far and has helped us find the best way to achieve the look we want. He's not the 'cheapest' installer out there, but he has a great reputation and it is very important that this part of the project be done well...so it's worth it.

Friday, November 28, 2008

Opening up the west wall

Well, I don't know why it took so long but we finally were able to cut the openings in the west wall (the existing brick masonry wall) that will house the new windows in the Dining Room & Living Room on the first floor and the bathroom on the second floor. Maybe the GC was waiting till the end so he could make a quick getaway when the whole house came crashing down. Ha, ha. But seriously, the whole process went fairly smooth and was fascinating to watch. The old wall held up nicely while they installed the concrete lintels. We tried to save most of the bricks but many of them broke during removal. The remnants will make their way to CWM's yard for crushing.























We have two big windows (side by side w/ a column in between that you can see in the upper right image) that will be going in the dining room wall and a long double awning that will be going high on the living room wall (this is the opening the guys are placing the lintel in and you can see it in the upper left image). The bottom left image shows the full opening for the windows in the bathroom at the second floor. These will actually be two casement side by side with a column in between (aligned with the windows above and below) but the column is not built yet.

The remaining windows will be installed on Saturday. We are so lucky to be able to have windows on the side of the house. I was amazed to see how much light the openings let into the first floor space. And although these windows are on the west wall and could get a lot of harsh western sun, we are benefiting greatly from the large shade tree next door as well as the neighboring houses that are tall enough (3-stories) to block much of the direct sun in the late afternoon but far enough away (roughly 20' due to the alley and their yards) to still allow plenty of light in.

Wednesday, November 26, 2008

The metal roof panels are in

The sheet metal fabricator/installer (Jason Pacetti) finished installing the Zalmag metal roof panels on the mansard today. We purchased the metal in coil stock (3 tightly wound rolls - 20"wide x 150' long) and then had the flat seam folded panels fabricated here in Philly. Every chance we get we try to have the raw materials shipped and then have a local fabricator make the product. There is still an embodied energy involved but this way we are injecting money into the local Philadelphia economy instead of having the products made somewhere else. Additionally, we form a relationship with local tradesmen.
















We are very happy with the roof and Jason did a great job on the panels. One lesson we learned here was that the next time we decide to use metal roof panels we will get the material in sheets (4'x8', for example) instead of coil. The reason we got the 20" wide coil was to maximize the material, eliminate waste, and it was a bit cheaper. Because we would not have to rip it (lengthwise) but simply cut the length of the panel we wanted (crosswise) as it was unrolled, there would be no waste. We ultimately wanted an 18"x36" panel. A 20"W piece of metal actually yields an 18"W panel after the two long edges are folded. So by cutting the roll into 38" pieces we would have our ideal size panel. Sounds easy enough, huh?

Not so much in the end. You see the material came wound so tightly that the fabricator had a really hard time straightening in out. He had some concern with "oil canning" (warping you sometimes see on metal roofs) since the panels were a fairly large size. He was going to try to "reverse roll it" but he felt it might get scratched. In the end, he had to work the metal a great deal to make the panels look good (and he did a great job and never raised his price). Also, when dealing with a coil you run the risk of any small dent or ding on the end of the coil repeating itself over and over as you unroll it.

Lastly, we are very pleased with the connection details (folded seams, turning of corners, meeting the windows, etc) that Jason came up with. He took the time to do it right. It is refreshing to work with someone who really cares about quality and gets excited about working on a project where the client cares as well.

We love the metal but would never get it in coil stock again if we planned on making flat panels. Next time, we figure if we can live with a 14"x30" panel we could divide up a 4'x8' sheet and have virtually no waste.

Here's a link to the metal (Zalmag) manufacturer: http://www.millenniumtiles.com/

Monday, November 24, 2008

Update on the roof hatch

Well, last week we finally said goodbye to our old plywood roof hatch. Our beautiful new hatch arrived last Monday and it took a total of about 20 minutes to install with some weatherstripping, silicone, and a few screws. The fit was perfect. It lets a ton of light into the space (not that it really needed it) and with the hydraulic arms, it opens very smoothly. I feel pretty confident about the insulation value due to the overlapped connection and the double insulated dome. I like the fact that it's not frosted, so on clear days and nights you can look up and see the sky. See previous post for full description of the hatch.


Sunday, November 23, 2008

All inspections passed

We have successfully passed all of our construction inspections. We are now ready for spray foam insulation (which will begin next week) and then drywall shortly after. There has been a lot of progress over the last week on other fronts too (stairs, the metal mansard, fiber-cement paneling, etc) which I will go over in the next few posts and try to get everyone up to speed.

Plumbing: Over the past two weeks we wrapped up all the piping and rough-ins and subsequently passed inspection (and we now have water). The whole process was a bit tricky due to the fact that we had the water shut off over a year ago because we knew weren't getting started for a while and didn't want to keep paying a bill. This meant the water department came and actually removed the meter from the house. Well, when our plumber gave us the original cost estimate he mentioned to us that he does not know the state of the pipe coming in from the street due to the fact that there is no meter and the water had been off for a while. This meant that he might have to tear up the sidewalk to make a new connection from the curb to the house and possibly from the curb to water main (under the street), if a lead pipe was still there. The cost incurred for all this work would be over $10K and has been hanging over us ever since receiving the estimate. We would not know what we had to do till the water department came out.

I remember the City tearing up the whole street a couple of years ago and replacing some lines but I never found out what exactly they replaced. The plumber's "worst case scenario" was that they replaced the water main and, since the house was abandoned at the time, they just cut off the connection which would then have to be replaced. Fortunately, we found that when PWD came last week to install a new meter, the pipes under the sidewalk appear to be in good shape (and still connected) and the pressure is good and steady...thus requiring no outside work. Whew! So the plumber came back and hooked up his main supply line to the meter and we are now in business. But the mystery street work remained.

Electrical: We passed our electrical inspection shortly after plumbing. This process involves a bit of orchestration too as, unlike the other trades, PECO doesn't actually do the electrical inspection. What they require is that an "independent underwriter" actually perform the inspection and then report to PECO when they are finished. PECO then comes out, checks to see verification from the underwriter, then (in our case) strings the line from the main power line running along the street to the front of the house. It is then our electrician's job to actually connect the wires from the street to the wires running up a conduit on the side of our house. Usually these are located on the front face of row houses, but we got lucky and were able to keep the conduit on the side since we're an end unit. And by the way, the owner can contact the underwriter directly. PECO has a short list of recommended ones, but our electrician has someone that he always works with and was able to come out on short notice. I recommend going this route, if possible, as you never know how long an underwriter will take if you are cold calling them.

At this point, we are still waiting for PECO to show up to run the wires. We were told this would be last Mon or Tues. but so far they haven't made an appearance. After PECO finishes their work and our electrician connects the two lines, we'll have power.

HVAC: There doesn't appear to be an official mechanical inspection, although we did find out that the City is now requiring everyone to get an HVAC "permit" (which they never did before). It costs about $500. We got our permit last Friday so we're good to go.

The mechanical contractor finished installing the furnace in the basement, which barely fit since we bumped up to a 14 SEER unit. I believe the units get bigger as you increase the SEER, so always keep that in mind when considering an upgrade. He also finished running the main return ducts and the supply ducts for the first floor...all running along the basement ceiling. He might have to come back later to tighten up a few things (tape joints, etc) but basically, he's done. I scheduled the gas company to come out tomorrow afternoon to install a new meter and turn the gas on. This is where the mystery street work was uncovered. It was the gas main that they replaced a couple of years ago and they did cut and cap the gas line to the house at the curb. So they have tear the sidewalk up in order to put a coupling on and reconnect our line to the street. Thankfully for us, PGW does this for free (unlike what the plumber was going to have to do).

The only snag in this process is that in order for the gas company to turn your gas on, they require at least one gas powered fixture in the house to be hooked up. Well, that's not a problem since the furnace is installed and ready to go. BUT, the furnace needs electricity to function and if the PWD gets there before PECO, well, then I guess we'll have to rig the furnace up to the generator (which I'm not even sure if this is possible). If not, then they will hook up the new meter and I will have to reschedule them to come back when we have power. ugh.

Also, regarding the ongoing battle about the city "requiring" everyone to put the gas meter on the front of the house (a total eye sore in addition to the fact that you then have to either protect it with bollards or box it in) there is at least one way to get around this. When doing a renovation project, the gas main is likely to be coming into the basement and that's where the old meter typically was. As much as possible, try not disturb this situation. They most likely will install the new meter where old one was because that's where the pipe is, thus solving the dilemma and getting your new meter in the basement.

Final Framing: This was the last official inspection (although the inspector still has to come back and check things out after insulation goes in.) We were asked to add some additional strapping to the roof rafters but that was about it. The inspector was very pleased with the solid construction and we in turn are very pleased to be done with ALL the inspections!

Wednesday, November 19, 2008

Open House scheduled

We decided the beginning of December will be a good time to have a "construction progress" OPEN HOUSE so folks can can come by and see first hand what we've been up to lately. The project will be at a point where all the systems are in and some of the drywall is up, but most importantly...we'll have heat and a working bathroom!

We still have a couple of months worth of work to do (install kitchen, flooring, trim work, fixtures, etc.) so we'll plan another open house to celebrate the final completion in the spring. In the interim, we thought it might be interesting to show the work-in-progress. We are going to try to make the event as educational as possible and, of course, we'll be on hand to give tours and answer any questions. All are welcome and bring your friends.

We'll be providing some refreshments (local cider, etc). See flier below for details. Everyone is welcome-spread the word!


Monday, November 3, 2008

Fabricator selected for steel stair

We have finally selected a fabricator for the steel stair that runs from the first to the second floor as well as all the related steel railings in the house. The work is now underway. This has been a long process which involved several quality bidders and a wide range of proposed bids.

Bill Curran (http://www.billcurrandesign.com/index.html) will be building and installing our stairs for us. Not only does Bill do beautiful work at a competitive price but he is also very accommodating and an extremely nice guy. He was also excited to be a part of our project and strongly supports what we're doing. We were immediately drawn to the clean, modern design sensibility of his work. Check out his site and make sure you scroll through all the images. His shop is in Philly just north of Chinatown, which he invited us to for our first design meeting. He lives above the shop in an amazing renovated industrial loft that basically acts as his showroom as he designed and fabricated almost all the furnishings (stairs, furniture, kitchen, etc). It was very impressive and very reassuring.

We have always had a pretty clear idea of what we wanted our stair to look like (and provided those details in the original set of drawings) and it was nice to find a high quality fabricator that was willing to build what we designed but was also able to help us refine the design and make it even better...and all within our budget. The basic design is fairly simple: an open riser stair with steel stringers, steel rod "ship-ladder" style railings, and wood treads. Very similar to the image below (which is from Bill's website.) The main difference is that we will have two stringers (opposed to the single, center stringer you see in the photo) and our railing posts are perpendicular to the top handrail, and the angle of the stair (opposed to perpendicular to the ground, as in the photo).


One important detail that we were always struggling with was the thickness of the wood tread. You see, when you have an open-riser stair, according to the residential building code, the open space between the top of one tread and the bottom of the next (essentially, part of the riser) cannot exceed 4" high (or as the code states: "must reject a 4" sphere"). Why a 4" sphere? Well, that's basically the size of a baby's head. This max. dimension was determined so that no one climbing the stairs could ever fall through the riser space. Makes sense. BUT, when your overall riser height is 7-3/4", the tread thickness (or the solid portion of the riser) needs to be a min. 3-3/4". Good luck finding wood that thick that is first, reasonably priced, and second, reclaimed timber. Basically, we needed a 4" x 10" (actual, not nominal) piece of wood. Over the past couple of months, this was proving to be a difficult find. Oh, and just so there's no confusion, the stair in the photo does not actually meet code and most likely received some sort of variance...which is totally feasible but we were trying to avoid any variances.

Also, the other drawback to this design was the tread was pretty bulky. So when we were going over all this with Bill, he presented a few possible alternatives. One of them involved adding a piece of steel that would connect the two steel angle supports (welded to the stringers that reach out to support the treads). This piece of steel would essentially run parallel with the tread nosing and set back about an inch. This allowed us to go back to a 2" thick wood tread and still meet code. The sketch below illustrates what I am talking about. The new steel piece is indicated in red.

One last detail that we went back and forth on was whether to go with 1/2" round rods or 1/2" square tubes for the balustrade. In the end, we decided on square as we thought it looked cleaner and aligned more with the overall design.

So how does sustainability factor into this feature? Well, there are a couple of different ways to approach a steel fabricated item such as a stair. One is to request that the item is made with salvaged steel. When doing something as precise and detailed as a stair, this can prove to be difficult because it will be hard to find the exact size and quantity of the pieces you need...never mind the condition the steel might be in if you plan on having them exposed. The other is to simply recognize that all steel that comes from a mill these days already has a high recycled content, sometimes up to 95%. And, of course, it's 100% recyclable. Therefore, simply choosing to build with steel is already a pretty green choice. So the main issue after that is to try and get your design locally fabricated. We have accomplished this. We are using another material in this stair though, and that is wood, for the treads. We will be acquiring reclaimed timbers (probably through our connection at Greenable) to use for the treads. The species will most likely be Chestnut, Elm, or Doug Fir.

And one last note. We also got Bill to fabricate us some steel posts for the railing up on the roof deck. For this rail we will be using stainless steel cables opposed to rods. This way, when your hanging out on the deck enjoying the green roof and the skyline views, the railing for the most part, simply disappears.

Wednesday, October 29, 2008

A blast from the past...

I know it's been quite a while since our last post but all that's about to change. We have a lot of things to discuss now including the fabrication of the main steel stair and railings (which is underway) along with the roof deck rails. We have some plumbing changes to talk about, some HVAC dilemmas, the ongoing kitchen design , some updates on finishing out the building envelope, a 'green' home tour, and many other things.

But for right now, we get back to "a blast from the past"...

So we are considering switching this blog over to Wordpress (which I will discuss later on) and I was going through some older post "edits" and saw this little gem that I had almost forgotten about. It was never published. It doesn't go into an incredible amount of detail but it should give you a sense of what we were doing 'way back when'. The post describes how we found the property, what we originally designed, and some of the process we went though early on.

Click HERE to view this previously unreleased post.

Wednesday, October 8, 2008

Some drywall options

I was looking into what kind of sustainable options we might have for drywall and I found some interesting products.

One option is a "paperless" drywall product by Georgia-Pacific called DensArmor Plus® Paperless Fiberglass Mat. It is a highly mold-and mildew- resistant interior gypsum panel. "DensArmor Plus panels feature fiberglass mats on both the front and the back for the best in interior protection from moisture currently available. The moisture-resistant fiberglass mats [also] make DensArmor Plus panels the ideal replacement for paper faced greenboard, where greenboard is still allowed by code."

One drawback I saw in using the DensArmor was the fact that it contains fiberglass and you would need to be careful when handling it. But the contractor indicated that this wouldn't really be a problem and shouldn't be a deciding factor. The only remaining drawback I found then, was cost. Based on what I found, a typical 4'x8' sheet of DensArmor drywall costs about 60% more than a standard drywall sheet. That's a pretty significant cost increase so we will have to see if we have that kind of room in the budget. The way things are going though...I don't know.


Another option I found was a very new product called Eco Rock by Serious Materials. Actually, this product is not even out yet (scheduled for release in late 2008). There are two major differences I see between Eco Rock and other drywall. First, it uses a large amount of post-industrial recycled content. And Second, it uses a lot less energy to produce.

From the Serious Materials website:

"Over 30 billion square feet of drywall are produced each year in the U.S. and Canada. A single sheet uses between 100,000 and 400,000 BTUs of energy to produce, depending on the age of the plant, producing 16 pounds of greenhouse gases per sheet. Approximately one-quarter of the cost of a gypsum drywall panel is tied to energy, with likely long-term cost increases; carbon taxes are common in Europe and may come to the U.S.

By contrast, EcoRock uses 80% less energy in the manufacturing of its core. No heaters or dryers are used in production, nor calcining processes – resulting in 80% less CO2. EcoRock also uses 85% post-industrial recycled content and is fully recyclable. A plant built for EcoRock reduces energy use to a minimum."

You might have heard of Serious Materials as they are the makers of Quiet Rock (a 'soundproof' drywall product). FYI...one sheet of Quiet Rock is acoustically equivalent to eight sheets of regular drywall. That's pretty amazing.

The Eco Rock product looks very promising but what I find even more compelling is the business philosophy held by Serious Materials' CEO, Kevin Surace. The following is a link to an article about him and his company (from about a year ago): Cleantech Article. Read it when you have a few minutes. I just wish there were a few more industry leaders like this around.



Wednesday, October 1, 2008

The reclaimed lumber, some plumbing progress, and the roof deck (sans railing)























Here are some images showing all of our salvaged lumber from the original house. It's being stored in the basement. On the taller stack, is the original pine flooring. This is all that was left after discarding what was rotten or severely damaged. The lower stack is all the salvaged 3x timbers. You can also see the old basement stair (which we have not figured out what to do with yet). All the lumber has been cleaned and de-nailed but still needs some work.

Then the planing begins...not all of it though, as we really like the dark "oxidized" look that the timbers have and might try to integrate some of these rough members into certain features of the house (i.e. built-ins, shelving, etc.)

As far as the pine flooring goes - although we are planning on using the carbonized strand bamboo for most of the floors in the house - we were thinking that it would be nice to lay the reclaimed pine floors up on the third floor (Master Suite) and limit the bamboo to the first two floors. If we determine that we don't have enough for the entire floor (which I fear we don't), we might just use it in either the Den or the Bedroom and have bamboo in the other. Then we could possibly use cork, in the connecting hallway, as a transition with tile being in the bathroom. All these materials are great but we need to be careful not to have too many flooring types in one area.

**An important note about re-laying hardwood floors: we have found that it's best not to plane the boards down (as tempting as it may be) before you re-lay them. The reason for this is that these boards are "tongue & groove" and once you start the planing process, you inevitable lose the centralized location of the T&G running along the side of the plank...and then you have real problems as the boards don't fit back together. This is because you will most likely plane more off of one side than the other. Your best bet is to simply re-lay the floors down in the state they are in on top of the new joists or sub-floor and then use a drum or orbital sander to take them down for refinishing. This is not the 'end-all-be-all' solution but it seems to be one with better odds for success.











Here's a shot of some plumbing progress (to show that it is actually happening!). On the left is the Kohler tub being installed in the second floor bathroom. The image on the right shows the ABS vent pipes heading up to the roof. The PEX is going in today and we should have running water by next week. Electrical and HVAC are also mobilizing now.



















Here's the roof deck. As you can see, it will take a little while for the vegetation to "integrate" with the deck. We are really happy with the way the deck came out and feel the end result will be truly unique. We should be getting the cable rail system in the next week or so. We still have our temporary roof hatch (a piece of plywood). The actual roof hatch will be arriving in a couple of weeks. The product we finally decided on is a custom sized, powder coated aluminum exterior and Birch wood interior hatch with a low-profile, double pane (insulated) clear acrylic panel and gas shock lifts. It is manufactured by a company called Insuladome (based in Long Island, NY) and ordered through Specialty Building Products (just outside of Philly). It's a great looking product that is well-built and priced very competitively (even for a custom size).

Thursday, September 11, 2008

The green roof is in!

Here are a few pics of the final installation. As you can see, we will need a couple of growing seasons before the roof gets filled in. The sedum plugs will mostly grow outward and fill in the spaces in between. If certain areas don't fill in adequately, the homeowner can always add more plugs later (although JIG does provide a maintenance warranty and will fill in rough spots in addition to weeding for 2 years after installation) . To most, this might not be what was expected when imagining the green roof...but as with many landscape features, it will take time to mature and will get better with age. You can order trays of mature plants (which we are interested in trying sometime) for the "instant" green roof (check out "Live Roof") but they tend to be more expensive and hey...you miss all the fun of growing your own roof from scratch!























A close up view of one of the larger plants and some of the other varieties. You gotta love the Philly skyline off in the distance. You can also see the tag of one of the main plant species and the contact info showing where it came from. Our sedums came from: Emory Knoll Farms. The wind protection (brown matting made from coconut husks) that is covering the dirt should only take about 1-2 years to completely biodegrade.












An overall shot of the roof area looking north. The piece of plywood in the middle is sitting on top of the deck area (which doesn't have the boards laid yet). You can also see the roof hatch opening near the middle and the A/C pad at the left.


















A view looking south. You can see the location of the black scupper box in the corner of the roof. The roof hatch (a double glazed, low profile dome) is being ordered and should arrive soon. We still need to trim up the felt around the edges and install the Zalmag metal cap flashing around the perimeter.

One of the frustrating timing issues we had was the fact that the green roof is finished now but we will not have running water in the house until at least a week from now. The roof needs to be watered fairly often in the first few weeks (then only periodically for the first couple of growing seasons, then it's pretty much self-sustaining). Let's just say that I have never prayed harder for rain than I did the last couple of days. And you know what? It worked. It rained steadily most of the day today (and is supposed to continue over the weekend). Our kind neighbor is allowing us to use their spicket next week until we have our own water. The plumber will install a hose bib on our roof at the exhaust chimney. We can then set up a watering system on a timer so we can keep the roof damp over the next few weeks.

The deck is being constructed with Everwood, an environmentally friendly, borate-based treated wood product, that is sold at Green Depot. We considered other options (including reclaimed wood) but Everwood seemed to achieve the durability levels and the price point that we were looking for. Composite decking (such as Trex) is also a nice green product but we remain big fans real wood for decks (kind of a vice in the 'green' world, I know, but at least it's non-toxic). The GC will be finishing the deck early next week (FYI: Green Depot stocks 2x6s of Everwood but has to order 2x4s as they are not as common for decks). I'll post some pics of the finished roof deck next week.

Wednesday, September 10, 2008

Green roof progress photos







Above left, you can see Howard (orange shirt) and Pat (black shirt) from JIG laying the first layer of felt down on top the root barrier. Above right, you can see the framework for the roof deck which will lay on top of the felt adjacent the roof hatch. After the felt, they will lay down the drainage mats.












Here the guys get ready to lift the large white bags of "media" (dirt) up to the roof. The bags will be suspended above roof, opened up, and the dirt evenly spread out on top of the drainage mats. You can also see the orange protective covering on the electrical lines in the image on the right.












To the left is a detail shot of the scupper drainage box at the rear (low point) of the roof. There are 3 long triangular shaped "raceway" drains underneath the roof media that channel water directly to the drain in the event of heavy rain. Good thing too, since it started pouring about halfway through the media installation process. Pat said the drains worked beautifully and dirt retained just the right amount of water. You can also see the river stone drainage beds and metal edging at the rear edge and around the roof hatch and exhaust shaft. The wood to the far right is the edge of roof deck sleeper system.



















All the dirt is down now and deck is in place. There is some final prep work with the edging and river stone before they lay the wind protection mat. If you look closely, you can see the small white ties coming out of the dirt that will hold the mat down. The plants have not arrive on site yet but are expected later in the day.


The roof is deck is not quite as big as we imagined it would be. It is 8' x 9' though, and should be enough to fit a small table and chairs or a couple of larger lounge chairs. In the end though, we think its a good size (relative to the overall area of the roof) because the bigger the deck gets, the less green roof there would be, which would end up being less cost effective and, seeing as there is no media under the deck, less effective with storm water management too.

Monday, September 8, 2008

Green roof installation begins

(for documentation purposes, I separated this post from the previous one)

This week, JIG will begin installing the green roof and our GC will begin constructing the roof deck. We are very excited about the fact that by the end of this week we'll have a green roof and a deck! You get so caught up in worrying about all the details sometimes when building a project that you forget to stop and enjoy the project once in a while. We'll...we feel this calls for a "topping off" party, which is now in the works. Who says they're just for "tall" buildings? And seeing that in about a month, the contractor's work will be done and it will be up to us (and a few very good friends) to finish out the house (which includes: installing all the plumbing fixtures, possibly the entire kitchen, the flooring and tile work, the wood trim, any lights that aren't recessed, and a few other minor details), we feel now might be a good a time as any to enjoy ourselves a bit since things are going to get very busy, very soon.

Back to the green roof... We had to scramble to get some last minute preparations taken care of before tomorrow - mainly the covering of the electrical wires out front (which can only be done by PECO) and laying down the EPDM root barrier. EPDM is a rubber-like membrane that comes in rolls and is mostly used as actual roofing membrane as it is waterproof and very durable. But it also makes a great root barrier, which is simply a barrier to keep the roots from damaging the actual roof membrane underneath. Of course, you can simply install a certain type of roof membrane that acts as both the waterproofing agent and the root barrier...but it's more expensive. Sorry if this is a bit confusing.

Anyways...the root barrier issue was a bit trickier due to the fact that it is "loose laid" (which means that it is not glued down to the roof membrane, as it not necessary in this case) and is best installed just before the green roof media is to be installed so there is no chance of damage to the membrane from folks working on it in addition to the fact that unless it is seriously weighted down, it could simply blow away. It's a very heavy membrane which means it could do a lot of damage if the wind ever happened to pick it up. And of course, on our project, these two tasks (laying the root barrier and installing the green roof) are done by separate contractors and thus prove challenging when the latter is supposed to start work first thing in Monday morning and a big storm is forecasted for the weekend, thus forcing the roofer to wait till the last minute to lay the membrane . Ugh! But everything seems to be working out okay...or so they tell me.

The reason we needed to cover the electrical wires is that JIG will be using a large mechanical lift (positioned in the street in front of the house) to get most of the material onto the roof. Covering the wires is simply a safety precaution in case anything or anyone should accidentally make contact with them.









To the best of my knowledge, the process of our green roof installation is as follows: First, the root barrier is laid down. Then they lay down a felt over the entire roof on top of the root barrier (except where the deck is going as this area gets a 1" deep hard plastic drainage, or "dimple", board - there is no media under the deck). Second comes the drainage mat (this has felt on the upside and a open plastic wire "tangle-weave" system about 1" thick on the downside) over all all the felt. They will also install the vertical metal edging that keeps the 8" wide river stone strip (at the front and rear edge) separate from the green roof area. The stone is for wind protection for the plants and for drainage. There is also a triangle conduit (or raceway) installed from the front of the roof to the back for drainage during heavy rains. Next comes the dirt. Then, in our case, due to the fact that we have a very low parapet, they will install a biodegradable wind protection mat (made from coconut husks...kind of like a burlap) which is tied down and keeps the plants roots in place until they are established. It takes about a year for the mat to completely disintegrate. Finally, they will cut about 900 small holes in the mat and plant all the sedum plugs in the holes. Talk about tedious work. All the while, the deck is being constructed (by our GC) and will be installed simultaneously with the dirt and plants (another scheduling challenge as it involves separate contractors). Timing these together is so the dirt and plants can blend nicely into the spaces between the staggered edges of the deck boards.

I am going to try to get pictures everyday this week to show all the progress. Should be a productive week!

Wednesday, September 3, 2008

Updated site plan and latest patio designs

Site Plan

A good friend and colleague, Britton Jones (a local landscape architect) helped us out with a design for the rear patio. He gave us a few different designs (which are all great and are posted below) to review along with a great reference book called Small Garden by John Brookes. If you have a small patio and are looking to do something very cool, you should definitely check it out. It has tons of great ideas. He was also able to recommend various types of durable, drought tolerant plants that we should use.

So after going over the various options with our friend and discussing the pros and cons of different elements and layouts, we decided on a plan that took what we feel are the best ideas from a couple of different designs. The patio portion of the site plan to the left incorporates the resultant plan (see enlarged plan to the right). One major change from our original idea was to move the rain garden from up against the house (under the kitchen window) to along the wall that divides our patio from the neighbors. This came from our desire to keep that water away from the foundation of the house and for the garden to be tied more directly to the rain barrel. The shade tree on axis with the back door and the main interior circulation path of the house is going to be very nice. Also, we have decided to use all the salvaged brick we have to pave the alley-way from the back patio to the front sidewalk (dirt, right now) instead of using it for the patio itself. The patio will instead have large concrete pavers that will be sand set on gravel with an "open joint" laid in a running bond pattern. The concrete pattern will begin to "break up" as it approaches the rear wall, allowing for greenery to emerge and help with water absorption. Thanks again, Britton, for your wonderful design ideas and suggestions.









The site plan also shows the extent of the green roof and design of the deck. The staggered edges of the wood deck reach out into the greenery and allow the boards to form a closer relationship between the two surfaces - blurring the edge between them as the plants mature. You can also see the location of the storm water planter at the edge of the front sidewalk where it meets the street. The purpose of the planter is explained in an earlier post.


Friday, August 22, 2008

The new (old) facade...

The mason FINALLY finished the new brick face. We used reclaimed brick from a salvage brick & stone place in Norristown. They are 100 yr old original Philly face brick from a few different jobs. The interesting thing about using reclaimed brick is...well, you never really know what your going to get (unless you lay the whole thing out beforehand, and...uhh, good luck with that.) We are generally very happy with the result. It has lot of character and tells a great story, in addition to being a very sustainable solution.

I suppose the only part that we weren't too happy about was the conglomeration of bright red bricks around the middle of the facade. We feel these were not mixed in to the rest as evenly as the blues, yellows, and blacks toward the bottom (which we love.) We took a chance by using old brick and we feel it was well worth it. Even the mason (who hated the idea all along) had to confess (begrudgingly) that he was very impressed with the final product and never imagined it could look this good. We even had a nice older woman by and say that she has lived in this neighborhood for over 50 years and has never seen anything quite like it. She loved it.

The only work left to do out front now is put in the reclaimed marble steps and then eventually redo the sidewalk.
















Now the question is: what to do, if anything, about all the bright red bricks? It's purely a question of aesthetics. And please...if anyone out there has an opinion on this, please let us know by leaving a comment. We are open for suggestions. Below is a concept we came up with (using Photoshop) where we could "tone down" the red brick and maybe bring a little bit of the blue, yellow, and black up to the top area. This could be achieved by stripping the paint off a few of the red bricks (using a great product from Dumond called Smart Strip by Peel Away) and then painting a few of the bricks up higher with matching blue, yellow, and black from the lower part. The purist side of me says "leave it alone, that's the way the cards fell and it's beautiful." But the developer side of me keeps reminding me that this is a spec house and has to have some degree of 'curb appeal" (as much as I hate that term.) Aesthetically speaking, we like the "after" version better but are torn by concept of messing with the quasi-chaotic purity of the whole process.

















ADDENDUM (8/27/08):
See image below. A good friend, "Dubin" (who has commented a few times on the blog) has helped out by taking a stab at another version...this one, going in the opposite direction by accentuating the color variations. Looks great! Maybe a bit crazy for our taste but we like what your thinking. Thanks for participating!

Thursday, August 14, 2008

Non-PVC drain pipe solution

So after many futile efforts of trying to find a non-PVC pipe that can be used for the drain lines in the house, I think I might have found a solution. I had been calling around to various plumbers, engineers and colleagues to try and find an alternative when, on a chance phone call to Superior Plumbing in South Philly, I was turned on to a product I hadn't heard of before. Now...the most ridiculous part: the product has actually been around for almost 50 years! It's a testimony to the fact when this industry finds something they like to work with (i.e cheap and easy like PVC) they seems to close off all other avenues and then become very resistant to change.

Here's what happened on the phone. I called the plumbing supplier (which I have used before and are great!) to ask if they know of any other pipe material besides PVC and cast iron that can be used for drain lines. He responded with an adamant, "No....that's it. Those are the only two." As I fained disbelief and pursued the question further, he held his ground. But just as I was thanking him for his assistance and was about to hang up the phone, he burst in with a "Hang on a second", and proceeded to ask another guy in the store to remind him what the name of that "black plastic pipe they use for drains" is. He came back with, "ABS". ABS?? What is that? He then informed me that ABS is an acceptable alternative but he didn't think of it right away because he doesn't stock it. "It's the stuff they make TVs and VCRs out of", he said. I asked if it was approved by the City of Philadelphia. He said, "Only for residential." I said, "Perfect." I then thanked the man again and began my usual background check.

An important aspect I found out was that ABS is actually a "thermoplastic", which means it is able to be safely recycled. This is not the case for PVC, which cannot effectively be recycled, as it is a difficult process, releases dangerous chemical when melted down, and needs more chemicals added in order to reform it.
ABS is derived from acrylonitrile, butadiene, and styrene. The advantage of ABS is that this material combines the strength and rigidity of the acrylonitrile and styrene polymers with the toughness of the polybutadiene rubber. The most important mechanical properties of ABS are resistance and toughness.

From the PPFA's (Plastic Pipe and Fittings Association) website: "ABS pipe and fittings are made from a thermoplastic resin called Acrylonitrile-Butadiene-Styrene (ABS for short). ABS PIPING SYSTEMS are easier and less expensive to install than metal piping; Feature superior flow due to smooth interiorfinish; Do not rot, rust, corrode or collect waste; Withstand earth loads and shipping (with properhandling); Resist mechanical damage, even at low temperatures; Perform at an operational temperature range of -40°F to 180°F; Are lightweight (one person can load and unload); Take less time to rough in than metal DWV materials."

ABS pipe and fittings were originally developed in the early 1950s for use in oil fields and the chemical industry. In 1959, John F. Long, a prominent Arizona builder, used ABS pipe in an experimental residence. Twenty-five years later, an independent research firm dug up and analyzed a section of the drain pipe. The result: no evidence of rot, rust or corrosion.

To see the PPFA's ABS Publications, click here You can also check out the FAQ's here.